|
FCC
EXTENDS 2 GHZ BAS RELOCATION DEADLINE
TV
TechCheck
of March 30, 2009, reported on the filing by Sprint Nextel,
the Association for Maximum Service Television, NAB, and the Society
of Broadcast Engineers to waive until February 2010 the deadline
by which Sprint Nextel must complete the relocation of the Broadcast
Auxiliary Service (BAS) licensees in the 1990-2025 MHz band. In
a Report and Order, released on June 12, 2009, the FCC
announced that it had granted the request to extend the deadline.
This removes the immediate concern that broadcasters who have
not yet completed the BAS transition could have lost access to
the BAS frequencies they currently use for ENG and/or studio-transmitter
links.
In addition
to waiving the deadline, the FCC publication includes an Order
related to the use of the freed-up spectrum by Mobile Satellite
Service (MSS) Operators, and also a Further Notice of Proposed
Rule Making about sharing of costs relating to relocation
of BAS incumbents, and other issues relating to completion of
the relocation process, including seeking comments on incentives
to encourage BAS licensees to complete the transition without
delay. Extracts from the FCC document follow.
In
this Report and Order and Order and Further Notice of
Proposed Rulemaking, we address the ongoing relocation of
the Broadcast Auxiliary Service (BAS) from the 1990-2110 MHz band
to the 2025-2110 MHz band. The rules and procedures we adopt,
as well as the modifications we propose, are crafted to ensure
the continuity of important BAS operations such as remote
newsgathering operations and studio-to-transmitter links
while completing a transition that will make 35 megahertz of valuable
spectrum available for many different new services by Mobile Satellite
Service (MSS) operators, Sprint Nextel Corporation (Sprint Nextel),
and future Advanced Wireless Services (AWS) licensees.
In the Report
and Order and Order, we:
- waive until February 8, 2010 the deadline by which Sprint
Nextel is required to complete the transition of the BAS incumbents
to frequencies above 2025 MHz;
- eliminate the requirement that MSS operators may not begin
operations until the relocation of BAS in the thirty largest
markets and all fixed BAS links in all markets is complete;
- address the interference environment during the period in
which both MSS and BAS operate in the 2000-2020 MHz band by
permitting the MSS entrants to conduct operations where the
BAS incumbents have not been relocated only if they successfully
coordinate with the BAS incumbents; and
- waive our rules governing when an MSS operator may provide
Ancillary Terrestrial Component (ATC) service in relation to
commercial satellite service.
In the Further
Notice of Proposed Rulemaking (Further Notice), we:
- tentatively conclude that MSS operators and future AWS licensees
will have an obligation to share, on a pro rata basis, in the
costs associated with the relocation of BAS incumbents if they
enter the band prior to the BAS sunset date of December
9, 2013;
- tentatively conclude that an MSS operator enters the
band and thus incurs an obligation to share in the costs
associated with relocation of BAS incumbents when its satellite
is found operational under its authorization milestone;
- seek comment on various approaches for when MSS operators
should be required to reimburse Sprint Nextel for their pro
rata shares of the relocation costs;
- invite additional analysis on whether MSS entrants can operate
on a secondary basis without coordination where BAS incumbents
have not been relocated;
- propose to clarify that MSS operators retain an obligation
to relocate BAS incumbents after the MSS operator begins operations;
and
- seek comment on incentives to continue to encourage BAS licensees
to complete the relocation process without unnecessary delay.
All of the
matters addressed herein relate to our fundamental goals of completing
the relocation of BAS operations from the 1990-2025 MHz band and
providing for the operation of new services on those frequencies.
The Commission
makes clear that this will be the last extension granted, and
that there will be consequences if the transition is not completed,
saying
we intend to exercise appropriate enforcement
action if Sprint Nextel is not able to complete the BAS transition
by February 8, 2010 for reasons it could have reasonably avoided,
we also believe that there should be appropriate consequences
for BAS licensees for failure to complete the relocation by the
new deadline.
Initially
there were eight MSS operators seeking to use the 2 GHz band,
but this has now declined to only two, New ICO Satellite Services
(ICO) and TerreStar Networks. ICO launched its satellite in April
2008, but it is not clear when it will be ready to start operations.
TerreStar has not yet launched its satellite.
The Report
and Order eliminates requirement that MSS operators may not
begin operations until the relocation of BAS in the thirty largest
markets and all fixed BAS links in all markets is complete. It
does, however, require that during the period in which both MSS
and BAS operate in the same part of the 2 GHz band, the MSS entrants
may conduct operations where the BAS incumbents have not been
relocated only if they successfully coordinate with the BAS incumbents.
Station engineers and local BAS frequency coordinators should
therefore anticipate the possibility they will be contacted by
the MSS companies to discuss potential interference issues, if
one or both MSS companies are ready to start operations during
this transition period.
Click
here for the full text of the Report and Order and
Order and Further Notice of Proposed Rule Making from the
FCC. Comments are due 21 days after the NPRM is published in the
Federal Register, which has not yet occurred. Click
here for the June 2009 BAS Relocation Project Progress Report
to the FCC. Further information on the 2 GHz relocation project
in general is at www.2ghzrelocation.com.
NAB
Satellite Uplink Operators Training Seminar
October 5 - 8, 2009 Washington, DC
This four-day course is designed to instruct about uplink operational
practices, which minimize the risk of satellite transmission interference.
This is an important course since the FCC rules require that a
trained operator be present at all times during transmissions,
either an earth station site or designated remote control point.
Go to the http://www.nab.org/satelliteSeminar/
or Contact NAB Science & Technology Department at (202) 429-5346
or ccolerid@nab.org for
information about the NAB Satellite Uplink Operators Training
Seminar. If you are interested in sponsorship opportunities for
this event contact NAB Advertising at (800) 521-8624 or advertising@nab.org.
The June 22, 2009 TV TechCheck is also available
in an Adobe Acrobat file.
Please click
here to read the Adobe Acrobat version of TV TechCheck.
|